Using FEA and hand calculations, we were able to help a nuclear utility evaluate RCP Seal Leakoff pipes and components for high temperature and pressure.
Projects
15 posts
We worked with a local utility to help design a foundation for a transformer. The design included the spill basin for transformer oil.
We developed a testing plan to test seals and determine their water resistance. A test rig was designed which put a static head on the sample flood seals.
We worked with a nuclear plant to optimize a shear wall design. The optimized design reduced the amount of rebar by about 30%.
Tornado generated missiles can wreak havoc, especially on a nuclear power plant. We helped one site design and optimize a protection system.